Construction Updates – January 2025

Update as on 8th January, 2025

Construction Updates – January 2025

Update as on 8th January, 2025

AURA - 1
AURA - 2
AURA - 3
ELARA - 1
ELARA - 2
NOVA
FLORA
Tower Updates
AURA

OC Received till 35th Floor

ELARA

OC Received till 35th Floor

NOVA

RCC 24th Slab Completed
Excavation Work Completed
Foundation (Raft) Work Completed
Basement Work Complete
STP and UG Tanks Civil Work Completed
Plinth Slab Completed
Basement Surround Waterproofing and Back filling Completed
Ground Floor Column Work Completed Till 24th Slab Work Completed.
OHT bottom slab work completed.
Block-work up to 23rd floor completed.
Plumbing Conceal Work up to 23rd Floor Completed.
Waterproofing up to 23rd Floor Completed
Gypsum Work completed till 22nd floors & 23rd floor work in progress.
Kitchen platform work completed till 21st floor & 22nd , 23rd floor work in progress.
Tiling work completed till 21st floor , 22nd & 23rd floor work in progress.
Door frame fixing work completed till 14th floor & 15th & 16th floor work in progress.
Fire fighting work till 22nd floor & 23rd floor work in progress
Surrounding Infra Work Started
Storm Water Drainage 75% Completed

FLORA

1st slab RCC work 
Excavation work completed
Foundation (Raft) work completed.
Periphery – retaining wall work completed.
STP and UG tank civil work completed
Pump room wall casting completed
Plinth slab completed.
1st slab RCC work completed & 1st floor (2nd floor ) slab RCC work completed
2nd floor Mivan setting work in progress.