Construction Updates – November 2024

Update as on 8th November, 2024

Construction Updates – November 2024

Update as on 8th November, 2024

AURA - 1
AURA - 2
AURA - 3
ELARA - 1
ELARA - 2
NOVA
FLORA
Tower Updates
AURA

OC Received till 35th Floor

ELARA

OC Received till 35th Floor

NOVA

RCC 24th Slab Completed
Excavation Work Completed
Foundation (Raft) Work Completed
Basement Work Complete
STP and UG Tanks Civil Work Completed
Plinth Slab Completed
Basement Surround Waterproofing and Back filling Completed
Ground Floor Column Work Completed Till 24th Slab Work Completed.
OHT bottom slab work completed.
Block-work up to 23rd floor completed.
Plumbing Conceal Work up to 23rd Floor Completed.
Waterproofing up to 22nd Floor Completed & 23rd Floor Work in Progress.
Gypsum Work completed till 22nd floors & 23rd floor work in progress.
Kitchen platform work completed till 16th floor & 17th , 18th floor work in progress.
Tiling work completed till 13th floor , 14th & 15th floor work in progress.
Door frame fixing work completed till 11th floor & 12th & 13th floor work in progress.
Fire fighting work till 22nd floor & 23rd floor work in progress
Surrounding Infra Work Started
Storm Water Drainage 60% Completed

FLORA

1st slab RCC work 
Excavation work completed
Foundation (Raft) work completed.
Periphery – retaining wall work completed.
STP and UG tank civil work completed
Pump room wall casting completed
Plinth slab completed.
1st slab RCC work completed
Typical Mivan setting work started