Construction Updates – August 2024

Update as on 5th August, 2024

Construction Updates – August 2024

Update as on 5th August, 2024

AURA - 1
AURA - 2
AURA - 3
ELARA - 1
ELARA - 2
NOVA
FLORA
Tower Updates
AURA

OC Received till 35th Floor

ELARA

OC Received till 35th Floor

NOVA

RCC 24th Slab Completed
Excavation Work Completed
Foundation (Raft) Work Completed
Basement Work Complete
STP and UG Tanks Civil Work Completed
Plinth Slab Completed
Basement Surround Waterproofing and Back filling Completed
Ground Floor Column Work Completed Till 24th Slab Work Completed.
OHT bottom slab work completed.
Block-work up to 23rd floor completed.
Plumbing Conceal Work up to 14th Floor Completed. 15th to 17th Floor Work in Progress.
Waterproofing up to 15th Floor Completed. 16th – 17th Floor Work in Progress.
Gypsum Work completed till 18th floors & 19th  floor work in progress.
Kitchen platform work completed till 8th floor & 9th , 10th floor work in progress.
Tiling work completed till 6th floor , 7th & 8th floor work in progress.
Door frame fixing work completed till 3rd floor & 4th & 5th floor work in progress.
Fire fighting work till 12th floor & 13th floor work in progress
Surrounding Infra Work Started
Storm Water Drainage 50% Completed

FLORA

Excavation Work Completed
Foundation (Raft) work completed.
Periphery – retaining wall work completed.
STP and UG tank civil work completed
Pump room wall casting completed
Plinth slab completed.
Ground floor column reinforcement in progress.