Construction Updates – December 2022

Update as on 4th December, 2022

Construction Updates – December 2022

Update as on 4th December, 2022

AURA - 1
AURA - 2
AURA - 3
ELARA - 1
ELARA - 2
NOVA
Tower Updates
Aura  RCC work up to 36th floor completed.
Lift machine room bottom slab completed & top slab 50% completed.
Block work completed till 32nd floor.
Plumbing Conceal work completed up to 30th Floor.
Gypsum work completed up to 30th Floor.
Waterproofing completed up to 30th Floor.
Electrical Conceal Work in block-work completed up to 30th Floor.
Door Frame fixing work completed up to 28th Floor.
Window rough ground marble fixing completed up to 28th Floor.
Window frames fixing 2nd to 10th floor completed, 11th to 14th floor 75% completed & 15th to 25th floor 50% work completed.
Window glass fixing 2nd to 7th floor completed, 8th to 14th floor 65% work completed & 15th -25th floor 25% completed.
Window sill fixing completed up to 28th floor.
Tiling & dado were completed up to the 30th floor.
Kitchen Platform fixing completed up to 28th floor.
Lift Lobby Tiling completed 1st to 27th-floor completed.
Staircase tiling 2nd floor to 27th-floor completed.
Painting primer and base coat putti work completed up to 27th floor.
Internal Duct Finishing (85% complete)
Service slab Plaster (90% complete)
External Plaster (85% Complete)
External surface preparation for paint (85% Complete)
External painting ( 45% completed)
Main door shutters 2nd to 10th floor 50% completed.
Bedroom door 2nd to 4th floor 25% completed.
Fire fighting horizontal 1st to 25th floor completed.
Fire fighting vertical 1st to 36th floor work in progress ( 75% completed).
Elara RCC work up to 36th floor completed.
Block work completed till 36th floor.
Lift machine room bottom slab completed.
Terrace floor tank top completed.
Plumbing Conceal work completed up to 35th Floor.
Gypsum work completed up to 35th Floor.
Waterproofing completed up to 35th Floor.
Electrical Conceal Work in block-work completed up to 35th Floor.
Door Frame fixing work completed up to 30th Floor.
Window rough ground marble fixing completed up to 30th Floor.
Window sill fixing completed up to 30th floor.
Window frames fixing 9th to 11th floor completed.
Window glass fixing 9th to 11th floor work 90% completed.
Tiling & dado were completed on the 35th floor.
Kitchen Platform fixing completed on 31st floor.
Lift Lobby Tiling work completed on 2nd, 3rd, 4th, 8th floor to 33rd floor.
Staircase tiling 2nd floor to 34th floor complete
Painting primer and base coat putti work completed 2nd floor to 29th floor.
Internal Duct Finishing (25% complete)
Service slab Plaster (85% complete)
External Plaster (75% Complete)
External surface preparation for paint (75% Complete)
Main door shutters 9th floor completed.
Fire fighting horizontal 9th to 25th floor completed & vertical 1st -36th floor work in progress ( 10% completed)
Nova Excavation work completed.
Foundation raft work completed.
Basement work completed.
STP & UG tank civil work completed
Plinth slab completed.
Ground floor column work 50% completed
Ground floor slab work started.

Marathon Referral and Loyalty Program

Refer your friends to any Marathon property and get rewards worth 1% of your friend’s flat cost. Your friend gets a discount too. It’s a win-win.