Construction Updates – December 2023

Update as on 4th December, 2023

Construction Updates – December 2023

Update as on 4th December, 2023

AURA - 1
AURA - 2
AURA - 3
ELARA - 1
ELARA - 2
NOVA
FLORA
Tower Updates
AURA

Completed RCC Works up to the 36th Floor
LMR Bottom Slab Completed
LMR Tanks Completed
Block-work Completed Till the 36th Floor
Plumbing Conceal Work Completed up to the 36th Floor
Gypsum Work Completed up to the 36th Floor.
Waterproofing Completed up to the 36th Floor.
Electrical Conceal Work in Block-Work Completed up to 36th Floor
Door Frame Fixing Work Completed up to 34th Floor.
Window Rough Ground Marble Fixing Completed up to 35th Floor
Window Frame Fixing Upto 35th Floor Completed
Window Glass Fixing Upto 35th Floor Completed
Window Sill Fixing Completed up to the 35th Floor
Tiling & Dado Were Completed up to the 35th Floor
Kitchen Platform Fixing Completed up to the 35th Floor
Lift Lobby Tiling Completed  Upto 35th Floor Complete
Staircase Tiling up to the 35th Floor Is Complete
1st coat paintung primer and base coat putti work completed up to the 33rd floor.
2nd coat painting primer & 2nd coat putti work completed upto the 33rd floor.
Internal Duct Finishing Completed
Service Slab Plaster Completed
External Plaster Completed
External Surface Preparation for Paint Completed
External Painting (95% Completed)
Fire Fighting Horizontal 1st to 36th Floor Completed
Fire Fighting Common Lobby Horizontal 1st to 36th Floor Completed
Fire Fighting Vertical Work Completed
Vertical Plumbing Completed
Main Door Shutters Upto 33rd Floor Completed
Bedroom Door Shutters Upto 33rd Floor Completed
Electrical Wire Pulling Upto 33rd Floor Completed
Electrical Switch Plate Upto 33rd Floor Completed
Electrical Db Dressing Work Upto 33rd Floor Completed
Electrical Substation Completed
Electrical Meter Room 95% Completed
Lift Installation for Lift-1 Completed and Lift-2 Completed, Pwd NOC Received, Lift-3 and Lift-4 Installation 95% Completed.
Electrical and Fire Duct FRD Door Fixing Upto 30th Floor Completed, 31st to 36th floor work in progress.
Staircase FRD  Door Fixing  Upto 30th Floor Completed, 31st to 36th floor work in progress.
Typical Lobby False Ceiling Framework Upto 30th Completed.
Typical Lift Lobby Electrification Upto 30th Floor Completed
Courtyard Hydrant Completed
Surrounding Infra 90% Completed
Fire Pumps and Panels 95% Completed
Rainwater Harvesting 90% Completed
STP  Completed
DG Sets With Connection 75% Completed
Solid Waste Compost Management Plant 85% Completed
Surrounds Plantation 25% Completed
Storm Water Drainage Completed

ELARA

Completed RCC Works up to the 36th Floor
LMR Bottom Slab Completed
LMR Tanks Completed
Block-work Completed Till the 36th Floor
Plumbing Conceal Work Completed up to the 36th Floor
Gypsum Work Completed up to the 36th Floor
Waterproofing Completed up to the 36th Floor
Electrical Conceal Work in Block-Work Completed up to 36th Floor
Door Frame Fixing Work Completed up to 33rd Floor
Window Rough Ground Marble Fixing Completed up to 35rd Floor
Window Frame Fixing Upto 35th Floor Completed
Window Glass Fixing Upto 34th Floor Completed
Tiling & Dado Were Completed up to the 35th Floor
Kitchen Platform Fixing Completed up to the 35th Floor
Lift Lobby Tiling Completed  Upto 35th Floor Complete
Staircase Tiling up to the 35th Floor is Complete
Painting Primer and Base Coat Putti Work Completed up to the 34th Floor.
Internal Duct Finishing Completed
Service Slab Plaster Completed
External Plaster Completed
External Surface Preparation for Paint Completed
Fire Fighting Horizontal work Completed
Fire Fighting Vertical Work Completed
Main Door Shutters Upto 33rd Floor Completed
Electrical Substation Completed
Electrical Meter Room 85% Completed
Lift Installation for Lift-1 Completed and Lift-2 Completed, Pwd NOC Received, Lift-3 and Lift-4 Installation 85% Completed.
Electrical and Fire Duct FRD Door Fixing Upto 30th Floor Completed, 31st to 36th floor work in progress.
Staircase FRD  Door Fixing  Upto 30th Floor Completed, 31st to 36th floor work in progress.
Typical Lobby False Ceiling bracketing Upto 25th Completed & Typical lobby false ceiling framework upto 15th floor.
Courtyard Hydrant Completed
Surrounding Infra 90% Completed
Fire Pumps and Panels 85% Completed
Rainwater Harvesting 85% Completed
STP Completed
DG Sets With Connection 75% Completed
Solid Waste Compost Management Plant 85% Completed
Surrounds Plantation 25% Completed
Storm Water Drainage Completed

NOVA

RCC 20th Slab Completed
Excavation Work Completed
Foundation (Raft) Work Completed
Basement Work Complete
STP and UG Tanks Civil Work Completed
Plinth Slab Completed
Basement Surround Waterproofing and Backfilling Completed
Ground Floor Column Work Completed Till 20th Slab Work Completed, 21st Slab Work in Progress(90% Completed)
Block-work upto 5th floor completed, 6th to 12th Floor 85% Complete
Plumbing Conceal Work on the 1st Floor Completed. 2nd Floor Work in Progress.
Waterproofing on the 1st Floor Completed. 2nd to 4th Floor Work in Progress.
Gypsum Work Started On 1st , 2nd to 12th Floors work in progress.
Surrounding Infra Work Started
Storm Water Drainage 50% Completed

FLORA

Excavation Work Completed
Foundation (Raft) work completed.
Retaining wall work started.