Construction Updates – February 2022
Update as on 2nd February, 2022
Construction Updates – February 2022
Update as on 2nd February, 2022
Tower | Updates |
---|---|
Aura | Detailed updates (Possession – Dec 2022): Completed RCC works up to 35th floor, 36th floor RCC work in progress (20 % Completed). Blockwork completed till 28th floor. Plumbing Conceal work completed up to 26th Floor. Gypsum work completed up to 24th Floor. Waterproofing completed up to 26th Floor. Electrical Conceal Work in blockwork completed up to 25th Floor. Door Frame fixing work completed up to 9th Floor. Window rough ground marble fixing completed up to 21st Floor. Window sill fixing completed up to 21st floor. Tiling & dado were completed upto the 23rd floor. Kitchen Platform fixing completed upto 21st floor. Painting base coat putty work completed upto 5th floor. Staircase tailing 2nd floor work in progress. (50% completed) Lift Lobby Tiling completed 3rd floor & 4th floor work in progress and 5th floor work in progress ( 50% completed). |
Elara | Detailed updates (Possession – June 2023): RCC work up to 35th floor completed., 36th floor RCC work in progress (60% Completed). Blockwork completed till 33rd floor. Plumbing Conceal work completed up to 33rd Floor. Gypsum work completed up to 30th Floor. Waterproofing completed up to 32nd Floor. Electrical Conceal Work in blockwork completed up to 33rd Floor. Door Frame fixing work completed up to 9th Floor. Window rough ground marble fixing completed up to 20th Floor. Window sill fixing completed up to 20th floor. Tiling & dado were completed on the 29th floor. Kitchen Platform fixing completed on 22nd floor. Internal Painting base coat putty work started. paintaing base coat putti work started. Lift Lobby Tiling work completed on 9th floor . 10th & 11th floor work in progress (60% Completed). |