Construction Updates – July 2023

Update as on 4th July, 2023

Construction Updates – Junly2023

Update as on 4th July, 2023

AURA - 1
AURA - 2
AURA - 3
ELARA - 1
ELARA - 2
NOVA
Tower Updates
Aura RCC work up to 36th floor completed.
Lift machine room bottom slab completed & tank 95% completed.
Block work completed till 36th floor.
Plumbing Conceal work completed up to 35th Floor.
Gypsum work completed up to 35th Floor.
Waterproofing completed up to 35th Floor.
Electrical Conceal Work in block-work completed up to 35th Floor.
Door Frame fixing work completed up to 33rd Floor.
Window rough ground marble fixing completed up to 33rd Floor.
Window frames fixing 2nd to 30th floor completed.
Window glass fixing 2nd to 25th floor completed.
Window sill fixing completed up to 33rd floor.
Tiling & dado were completed up to the 35th floor.
Kitchen Platform fixing completed up to 33rd floor.
Lift Lobby Tiling completed 1st to 32nd floor completed.
Staircase tiling 2nd floor to 32nd floor completed.
1st coat painting primer and base coat putti work completed up to 27th floor. 2nd coat painting primer & putti work completed up to 25th floor.
Internal Duct Finishing completed.
Service slab Plaster completed.
External Plaster (95% Complete)
External surface preparation for paint (95% Complete)
External painting ( 95% completed)
Vertical plumbing 85% completed.
Main door shutters 2nd to 25th floor completed.
Bedroom door 2nd to 25th floor completed.
Electrical wire pulling 2nd to 25th floor completed.
Electrical switch plate 2nd to 25th floor completed.
Electrical DB work till 25th floor completed.
Electrical substation 100% completed.
Electrical meter room 60% completed.
Electrical & fire duct FRD door fixing 1st to 20th floor completed.
Staircase FRD door fixing started.
Typical lobby false ceiling & electrification work started .
Lift installation for lift 1 completed ,lift 2 completed PWD certificate received & lift 3 & 4 installation 50% completed.
Fire fighting common lobby horizontal 1st to 35th floor completed.
Fire fighting vertical 1st to 36th floor completed.
Elara RCC work up to 36th floor completed.
Block work completed till 36th floor.
Lift machine room bottom slab completed.
Terrace floor tank top completed.
Plumbing Conceal work completed up to 35th Floor.
Gypsum work completed up to 35th Floor.
Waterproofing completed up to 35th Floor.
Electrical Conceal Work in block-work completed up to 35th Floor.
Door Frame fixing work completed up to 30th Floor.
Window rough ground marble fixing completed up to 33rd Floor.
Window frames fixing 2nd to 25th floor completed.
Window glass fixing 2nd to 25th floor work completed.
Tiling & dado were completed on the 35th floor.
Kitchen Platform fixing completed on 33rd floor.
Lift Lobby Tiling work completed on 2nd to 34th floor.
Staircase tiling 2nd floor to 34th floor complete
Painting primer and base coat putti work completed 2nd floor to 29th floor.
Internal Duct Finishing (85% complete)
Service slab Plaster (90% complete)
External Plaster (90% Complete)
External surface preparation for paint (85% Complete)
Main door shutters 9th to 17th floor completed.
Electrical substation 100% completed & meter room 10% completed.
Lift installation for lift 1 & lift 2 completed & PWD certificate received & lift 3 & lift 4 installation started .
Electrical & fire duct FRD door fixing started.
Staircase FRD door fixing started.
Typical lobby false ceiling & electrification work started.
Fire fighting horizontal 9th to 29th floor completed & vertical 1st -36th floor work completed.
Nova RCC 6th slab completed
Foundation raft work completed.
Basement work completed.
STP & UG tank civil work completed
Plinth slab completed.
Basement surround waterproofing & back filling completed.
Ground floor column work completed till 6th slab & 7th slab work in progress ( 80% completed )
Blockwork on 1st floor started.
Plumbing conceal work completed till 1st floor.
Waterproofing work started on 1st floor.

Marathon Referral and Loyalty Program

Refer your friends to any Marathon property and get rewards worth 1% of your friend’s flat cost. Your friend gets a discount too. It’s a win-win.