Construction Updates – June 2024

Update as on 5th June, 2024

Construction Updates – June 2024

Update as on 5th June, 2024

AURA - 1
AURA - 2
AURA - 3
ELARA - 1
ELARA - 2
NOVA
FLORA
Tower Updates
AURA

OC Received till 35th Floor

ELARA

OC Received till 35th Floor

NOVA

RCC 24th Slab Completed
Excavation Work Completed
Foundation (Raft) Work Completed
Basement Work Complete
STP and UG Tanks Civil Work Completed
Plinth Slab Completed
Basement Surround Waterproofing and Back filling Completed
Ground Floor Column Work Completed Till 24th Slab Work Completed.
OHT bottom slab work completed.
Block-work up to 23rd floor completed.
Plumbing Conceal Work up to 9th Floor Completed. 10th Floor Work in Progress.
Waterproofing up to 9th Floor Completed. 10th Floor Work in Progress.
Gypsum Work completed till 12th floors & 13th and 14th floor work in progress.
Kitchen platform work completed on 3rd floor & 4th t 6th floor work in progress.
Tiling work completed on 3rd floor & 4th floor work in progress.
Surrounding Infra Work Started
Storm Water Drainage 50% Completed

FLORA

Excavation Work Completed
Foundation (Raft) work completed.
Periphery – retaining wall work completed.
STP and UG tank civil work completed
Pump room wall casting completed
Plinth slab shuttering work in progress.