Construction Updates – March 2022
Update as on 2nd March, 2022
Construction Updates – March 2022
Update as on 2nd March, 2022
Tower | Updates |
---|---|
Aura | Detailed updates (Possession – Dec 2022): Completed RCC works up to 35th floor, 36th floor RCC work in progress (20 % Completed). Blockwork completed till 28th floor. Plumbing Conceal work completed up to 26th Floor. Gypsum work completed up to 25th Floor. Waterproofing completed up to 27th Floor. Electrical Conceal Work in blockwork completed up to 27th Floor. Door Frame fixing work completed up to 19th Floor. Window rough ground marble fixing completed up to 21st Floor. Window sill fixing completed up to 21st floor. Tiling & dado were completed upto the 23rd floor. Kitchen Platform fixing completed upto 21st floor. Painting base coat putty work completed upto 10th floor. Staircase tailing 2nd floor to 8th floor completed ,9th floor work in progress. (50% completed) Lift Lobby Tiling completed 2nd floor to 8th floor and 9th floor work in progress ( 90% completed). |
Elara | Detailed updates (Possession – June 2023): RCC work up to 35th floor completed., 36th floor RCC work in progress (60% Completed). Blockwork completed till 33rd floor. Plumbing Conceal work completed up to 33rd Floor. Gypsum work completed up to 30th Floor. Waterproofing completed up to 33rd Floor. Electrical Conceal Work in blockwork completed up to 33rd Floor. Door Frame fixing work completed up to 9th Floor. Window rough ground marble fixing completed up to 21st Floor. Window sill fixing completed up to 21st floor. Tiling & dado were completed on the 30th floor. Kitchen Platform fixing completed on 23rd floor. painting base coat putti work completed 2nd floor to 12th floor. Lift Lobby Tiling work completed on 9th floor to 14th floor . 15th floor work in progress (60% Completed). |