Construction Updates – March 2024

Update as on 11th March, 2024

Construction Updates – March 2024

Update as on 11th March, 2024

AURA - 1
AURA - 2
AURA - 3
ELARA - 1
ELARA - 2
NOVA
FLORA
Tower Updates
AURA

Completed RCC Works up to the 36th Floor
LMR Bottom Slab Completed
LMR Tanks Completed
Block-work Completed Till the 36th Floor
Plumbing Conceal Work Completed up to the 36th Floor
Gypsum Work Completed up to the 36th Floor.
Waterproofing Completed up to the 36th Floor.
Electrical Conceal Work in Block-Work Completed up to 36th Floor
Door Frame Fixing Work Completed up to 36th Floor.
Window Rough Ground Marble Fixing Completed up to 36th Floor
Window Frame Fixing Upto 36th Floor Completed
Window Glass Fixing Upto 36th Floor Completed
Window Sill Fixing Completed up to the 36th Floor
Tiling & Dado Were Completed up to the 36th Floor
Kitchen Platform Fixing Completed up to the 36th Floor
Lift Lobby Tiling Completed  Upto 36th Floor Complete
Staircase Tiling up to the 36th floor is Complete
1st coat painting primer and base coat putti work completed up to the 36th floor.
2nd coat painting primer & 2nd coat putti work completed upto the 36th floor.
Internal Duct Finishing Completed
Service Slab Plaster Completed
External Plaster Completed
External Surface Preparation for Paint Completed
External Painting (95% Completed)
Fire Fighting Horizontal Completed
Fire Fighting Common Lobby Horizontal Completed
Fire Fighting Vertical Work Completed
Vertical Plumbing Completed
Main Door Shutters Upto 36th Floor Completed
Bedroom Door Shutters Upto 36th Floor Completed
Electrical Wire Pulling Upto 36th Floor Completed
Electrical Switch Plate Upto 36th Floor Completed
Electrical Db Dressing Work Upto 36th Floor Completed
Electrical Substation Completed
Electrical Meter Room 95% Completed
Lift Installation for Lift-1 Completed and Lift-2 Completed, PWD NOC Received, Lift-3 and Lift-4 Installation Completed PWD NOC in process, Lift 5 & 6 installation 30% completed.
Electrical and Fire Duct FRD Door Fixing Upto 35th Floor Completed.
Staircase FRD  Door Fixing  Upto 35th Floor Completed
Typical Lobby False Ceiling Framework Upto 36th Completed.
Typical Lift Lobby Electrification Upto 36th Floor Completed
Courtyard Hydrant Completed
Surrounding Infra 90% Completed
Fire Pumps and Panels 95% Completed
Rainwater Harvesting Completed
STP  Completed
DG Sets With Connection 95% Completed
Solid Waste Compost Management Plant 99% Completed
Surrounds Plantation 50% Completed
Storm Water Drainage Completed

ELARA

Completed RCC Works up to the 36th Floor
LMR Bottom Slab Completed
The terrace floor tank top Completed
Block-work Completed Till the 36th Floor
Plumbing Conceal Work Completed up to the 36th Floor
Gypsum Work Completed up to the 36th Floor
Waterproofing Completed up to the 36th Floor
Electrical Conceal Work in Block-Work Completed up to 36th Floor
Door Frame Fixing Work Completed up to 36th Floor
Window Rough Ground Marble Fixing Completed up to 36th Floor
Window Frame Fixing Upto 35th Floor Completed
Window Glass Fixing Upto 35th Floor Completed
Tiling & Dado Were Completed up to the 36th Floor
Kitchen Platform Fixing Completed up to the 36th Floor
Lift Lobby Tiling Completed  Upto 36th Floor Complete
Staircase Tiling up to the 36th Floor is Complete
Painting Primer and Base Coat Putti Work Completed up to the 36th Floor.
Electrical wire pulling up to 36th floor completed.
Electrical switch plate up to 36th floor completed.
Internal Duct Finishing Completed
Service Slab Plaster Completed
External Plaster Completed
External Surface Preparation for Paint Completed
Fire Fighting Horizontal work Completed
Fire Fighting Vertical Work Completed
Main Door Shutters Upto 36th Floor Completed
Electrical Substation Completed
Electrical Meter Room 95% Completed
Lift Installation for Lift-1 Completed and Lift-2 Completed, Pwd NOC Received, Lift-3 and Lift-4 Installation 85% Completed, PWD NOC in progress.
Electrical and Fire Duct FRD Door Fixing Upto 35th Floor Completed.
Staircase FRD  Door Fixing  Upto 36th Floor Completed.
Typical Lobby False Ceiling bracketing Upto 35th Completed & Typical lobby false ceiling framework upto 35th floor.
Courtyard Hydrant Completed
Surrounding Infra 90% Completed
Fire Pumps and Panels 90% Completed
Rainwater Harvesting Completed
STP Completed
DG Sets With Connection 95% Completed
Solid Waste Compost Management Plant 99% Completed
Surrounds Plantation 50% Completed
Storm Water Drainage Completed

NOVA

RCC 24th Slab Completed
Excavation Work Completed
Foundation (Raft) Work Completed
Basement Work Complete
STP and UG Tanks Civil Work Completed
Plinth Slab Completed
Basement Surround Waterproofing and Back filling Completed
Ground Floor Column Work Completed Till 24th Slab Work Completed.
Block-work upto 22nd floor completed.
Plumbing Conceal Work up to 4th Floor Completed. 5th Floor Work in Progress.
Waterproofing upto 4th Floor Completed. 5th Floor Work in Progress.
Gypsum Work completed On 1st floor to 7th floors & 8th floor work in progress. (50% completed)
Kitchen platform work of 1st floor in progress.
Tiling work completed on 1st floor
Surrounding Infra Work Started
Storm Water Drainage 50% Completed

FLORA

Excavation Work Completed
Foundation (Raft) work completed.
Basement work & STP wall casting in progress.