Construction Updates – May 2022
Update as on 10th May, 2022
Construction Updates – May 2022
Update as on 10th May, 2022
Tower | Updates |
---|---|
Aura | Detailed updates (Possession – Dec 2022): Completed RCC works up to 35th floor, 36th floor RCC work in progress (50 % Completed). Blockwork completed till 29th floor. Plumbing Conceal work completed up to 27th Floor. Gypsum work completed up to 26th Floor. Waterproofing completed up to 27th Floor. Electrical Conceal Work in blockwork completed up to 27th Floor. Door Frame fixing work completed up to 24th Floor. Window rough ground marble fixing completed up to 23rd Floor. Window sill fixing completed up to 23rd floor. Tiling & dado were completed upto the 27th floor. Kitchen Platform fixing completed upto 27th floor. Painting base coat putty work completed upto 20th floor. Staircase tailing 2nd floor to 26th floor completed ,27th floor work in progress. (50% completed) Lift Lobby Tiling completed 2nd floor to 26th floor and 27th and 28th floor work in progress ( 50% completed). |
Elara | Detailed updates (Possession – June 2023): RCC work up to 36th floor completed. Blockwork completed till 33rd floor. Plumbing Conceal work completed up to 33rd Floor. Gypsum work completed up to 31st Floor. Waterproofing completed up to 33rd Floor. Electrical Conceal Work in blockwork completed up to 33rd Floor. Door Frame fixing work completed up to 27th Floor. Window rough ground marble fixing completed up to 23rd Floor. Window sill fixing completed up to 23rd floor. Tiling & dado were completed on the 31st floor. Kitchen Platform fixing completed on 25th floor. painting base coat putti work completed 2nd floor to 22nd floor. Lift Lobby Tiling work completed on 9th floor to 29th floor . 30th floor work in progress (30% Completed). |
Marathon Referral and Loyalty Program
Refer your friends to any Marathon property and get rewards worth 1% of your friend’s flat cost. Your friend gets a discount too. It’s a win-win.