Construction Updates – May 2024

Update as on 7th May, 2024

Construction Updates – May 2024

Update as on 7th May, 2024

AURA - 1
AURA - 2
AURA - 3
ELARA - 1
ELARA - 2
NOVA
FLORA
Tower Updates
AURA

OC Received till 35th Floor

ELARA

OC Received till 35th Floor

NOVA

RCC 24th Slab Completed
Excavation Work Completed
Foundation (Raft) Work Completed
Basement Work Complete
STP and UG Tanks Civil Work Completed
Plinth Slab Completed
Basement Surround Waterproofing and Back filling Completed
Ground Floor Column Work Completed Till 24th Slab Work Completed.
Block-work up to 22nd floor completed.
Plumbing Conceal Work up to 6th Floor Completed. 7th Floor Work in Progress.
Waterproofing upto 9th Floor Completed. 10th Floor Work in Progress.
Gypsum Work completed till 9th floors & 10th floor work in progress.
Kitchen platform work completed on 2nd floor & 3rd floor work in progress.
Tiling work completed on 1st floor & 2nd floor work in progress.
Surrounding Infra Work Started
Storm Water Drainage 50% Completed

FLORA

Excavation Work Completed
Foundation (Raft) work completed.
Basement work & STP wall casting in progress, Periphery 65-70% of the retaining wall work completed.
Pump room wall casting completed
Casting of tank slab work in progress.