Construction Updates – October 2021

Construction Updates – October 2021

AURA - 1
ELARA - 1
AURA - 2
ELARA - 2
AURA - 3
Tower Updates
Aura Detailed updates (Possession – Dec 2022):
Completed RCC work upto 27th floor, 28th floor RCC work in progress (45 % Completed).
Blockwork completed till 22nd floor.
Plumbing Conceal work completed upto 21st Floor.
Gypsum work completed upto 21st Floor.
Waterproofing completed upto 21st Floor.
Electrical Conceal Work in block work completed upto 21st Floor.
Door Frame fixing work completed upto 4th Floor.
Window rough ground marble fixing completed upto 21st Floor.
Window sill fixing completed upto 21st floor.
Tiling & dado completed in 195 Flats..
Kitchen Platform fixing completed in 195 Flats.
Elara Detailed updates (Possession – June 2023):
RCC work upto 31st floor completed, 32nd floor RCC work in progress (20% Completed).
Blockwork completed till 26th floor.
Plumbing Conceal work completed upto 20th Floor.
Gypsum work completed upto 20th Floor.
Waterproofing completed upto 22nd Floor.
Electrical Conceal Work in block work completed upto 24th Floor.
Door Frame fixing work completed upto 2nd Floor.
Window rough ground marble fixing completed upto 6th floor.
Window sill fixing completed upto 6th floor.
Tiling & dado completed in 36 flats.
Kitchen Platform fixing completed in 56 Flats.