Construction Updates – October 2024

Update as on 5th October, 2024

Construction Updates – October 2024

Update as on 5th October, 2024

AURA - 1
AURA - 2
AURA - 3
ELARA - 1
ELARA - 2
NOVA
FLORA
Tower Updates
AURA

OC Received till 35th Floor

ELARA

OC Received till 35th Floor

NOVA

RCC 24th Slab Completed
Excavation Work Completed
Foundation (Raft) Work Completed
Basement Work Complete
STP and UG Tanks Civil Work Completed
Plinth Slab Completed
Basement Surround Waterproofing and Back filling Completed
Ground Floor Column Work Completed Till 24th Slab Work Completed.
OHT bottom slab work completed.
Block-work up to 23rd floor completed.
Plumbing Conceal Work up to 20th Floor Completed. 21st to 23rd Floor Work in Progress.
Waterproofing up to 20th Floor Completed. 21st to 23rd Floor Work in Progress.
Gypsum Work completed till 21st floors & 22nd floor work in progress.
Kitchen platform work completed till 14th floor & 15th , 16th floor work in progress.
Tiling work completed till 11th floor , 12th & 13th floor work in progress.
Door frame fixing work completed till 11th floor & 12th & 13th floor work in progress.
Fire fighting work till 20th floor & 21st & 22nd  floor work in progress
Surrounding Infra Work Started
Storm Water Drainage 50% Completed

FLORA

1st slab RCC work 
Excavation work completed
Foundation (Raft) work completed.
Periphery – retaining wall work completed.
STP and UG tank civil work completed
Pump room wall casting completed
Plinth slab completed.
1st slab RCC work completed