Construction Updates – September 2023
Update as on 4th September, 2023
Construction Updates – September 2023
Update as on 4th September, 2023
Tower | Updates |
---|---|
Aura | RCC work up to 36th floor completed. Lift machine room bottom slab & LMR tanks completed. Block work completed till 36th floor. Plumbing Conceal work completed up to 36th Floor. Gypsum work completed up to 35th Floor. Waterproofing completed up to 35th Floor. Electrical Conceal Work in block-work completed up to 35th Floor. Door Frame fixing work completed up to 33rd Floor. Window rough ground marble fixing completed up to 33rd Floor. Window frames fixing 2nd to 33rd floor completed. Window glass fixing 2nd to 33rd floor completed. Window sill fixing completed up to 33rd floor. Tiling & dado were completed up to the 35th floor. Kitchen Platform fixing completed up to 34th floor. Lift Lobby Tiling completed 1st to 34th floor completed. Staircase tiling 2nd floor to 33rd floor completed. 1st coat painting primer and base coat putti work completed up to 27th floor. 2nd coat painting primer & putti work completed up to 25th floor. Internal Duct Finishing completed. Service slab Plaster completed. External Plaster (95% Complete) External surface preparation for paint (95% Complete) External painting ( 95% completed) Vertical plumbing 95% completed. Main door shutters 2nd to 30th floor completed. Bedroom door 2nd to 30th floor completed. Electrical wire pulling 2nd to 25th floor completed. Electrical switch plate 2nd to 25th floor completed. Electrical DB work till 25th floor completed. Electrical substation 100% completed. Electrical meter room 80% completed. Electrical & fire duct FRD door fixing 1st to 25th floor completed. Staircase FRD door fixing 1st to 25th floor completed. Typical lobby false ceiling framework 1st to 25th completed . Typical lift lobby electrification 4th floor completed. Lift installation for lift 1 completed ,lift 2 completed PWD certificate received & lift 3 & 4 installation 75% completed. Fire fighting common lobby horizontal 1st to 36th floor completed. Fire fighting vertical 1st to 36th floor completed. |
Elara | RCC work up to 36th floor completed. Block work completed till 36th floor. Lift machine room bottom slab completed. Terrace floor tank top completed. Plumbing Conceal work completed up to 36th Floor. Gypsum work completed up to 36th Floor. Waterproofing completed up to 36th Floor. Electrical Conceal Work in block-work completed up to 35th Floor. Door Frame fixing work completed up to 33rd Floor. Window rough ground marble fixing completed up to 33rd Floor. Window frames fixing 1st to 33rd floor completed. Window glass fixing 1st to 33rd floor work completed. Tiling & dado were completed on the 35th floor. Kitchen Platform fixing completed on 34th floor. Lift Lobby Tiling work completed on 1st to 34th floor. Staircase tiling 1st floor to 34th floor complete Painting primer and base coat putti work completed 2nd floor to 29th floor. Internal Duct Finishing (95% complete) Service slab Plaster (95% complete) External Plaster (90% Complete) External surface preparation for paint (90% Complete) Main door shutters 1st to 30th floor completed. Electrical substation 100% completed & meter room 10% completed. Lift installation for lift 1 & lift 2 completed & PWD certificate received & lift 3 & lift 4 installation 50% completed . Electrical & fire duct FRD door fixing 50% completed. Electrical wire pulling 1st to 25th floor work completed. Electrical switch plate 1st to 24th floor completed. Staircase FRD door fixing 50% completed. Typical lobby false ceiling bracketing 1st to 22nd floor completed. Typical lift lobby electrification started. Fire fighting horizontal 1st to 33rd floor completed & vertical 1st to 36th floor work completed. |
Nova | RCC 12th slab completed Excavation work completed. Foundation raft work completed. Basement work completed. STP & UG tank civil work completed Plinth slab completed. Basement surround waterproofing & back filling completed. Ground floor column work completed till 12th slab & 13th slab work in progress ( 40% completed ) Block work on 1st to 3rd floor 85% completed. Plumbing conceal work completed till 1st floor. Waterproofing 1st floor work completed. |
Marathon Referral and Loyalty Program
Refer your friends to any Marathon property and get rewards worth 1% of your friend’s flat cost. Your friend gets a discount too. It’s a win-win.